Mid-Halton Wastewater Treatment Plant - Improving Wastewater Systems

Location:

Town of Oakville

Project Type:

Wastewater

Improvements:

Halton Region is expanding the facilities of the Mid-Halton Wastewater Treatment Plant. These improvements will include the following features:

  • Increasing plant capacity
  • New ultraviolet (UV) disinfection system
  • Expansion of plant operations and administration area
  • Expansion of North Pumping Station
  • New primary digester
Project Status:

Administration area in progress

Start Date:
End Date
:

April 2017
September 2018

Project #

S-2583C